Project Renovation

Project 2 Renovation

Project Performance

All thanks be to Allah, with the incredible fundraising effort performed in ​Ramadan of 2023, we successfully raised enough funds to renovate the bathroom at our current location. May Allah continue to Bless and increase in reward the dedicated donors who have been assisting with the achievement of our improvement goals.

The current project is underway and below is a progress of our milestones.
Phase 1: Fundraising Effort | Ramadan 2023 (COMPLETED)
Phase 2: Renovation Planning | May-Aug 2023 (COMPLETED)
Phase 3: Contractor Selection | Aug-Jan 2024 (COMPLETED)
Phase 4: Project Kickoff | Feb 02, 2024 (COMPLETED)
Phase 5: Project Execution (COMPLETED)
Phase 6: Review and Completion (COMPLETED)
Below are some metrics to help visualize the project's performance over the period of execution:
  • Project Completion Status: 50%
  • Cost
    • Budget Cost Estimate: $43,000.00
    • Actual Cost at Completion: TBD
  • ​Schedule
    • ​Anticipated Date of Completion: March 08, 2024
    • Actual Date of Completion: April 08, 2024